(a)[2]
Complete nodes 5 and 6 on the network diagram below (reproduced from the Insert).
(b)[2]
Calculate the total float for Activity F.
(c)[12]
Evaluate the benefit to IPA of Critical Path Analysis (CPA) as a management tool for planning operations.