Business 9609 · AS & A Level · Quality management

Quality management — practice question

(a)[8]

Use the network diagram in Fig. 1 and Table 2 in the Insert.

  • Finish the network diagram at nodes 3 and 4. [4]
  • State which activities lie on the critical path. [1]
  • State the shortest time needed to complete the opening of the new café. [1]
  • Calculate the free float for Activity F. [2]
(b)[12]

Use your answers to 2(a) and any other information. Discuss whether PY’s directors ought to be confident that the café in city X will be open in time for the summer season.

Worked solution & mark scheme

This 20-mark question has a full step-by-step worked solution and mark scheme.

  • Full mark scheme, point by point
  • Step-by-step worked solution
  • Write your answer & get it marked instantly by AI