The table gives the work done and the time spent by four machines. Which machine is the most powerful?
- Awork done $= 100\ \text{kJ}$, time taken $= 10\ \text{s}$
- Bwork done $= 100\ \text{kJ}$, time taken $= 20\ \text{s}$
- Cwork done $= 200\ \text{kJ}$, time taken $= 10\ \text{s}$
- Dwork done $= 200\ \text{kJ}$, time taken $= 20\ \text{s}$