Look at Figure 1.1:
(a(i))[3]

Calculate the total float available for activity C.

(a(ii))[1]

Identify the minimum project duration from the information given.

(b)[12]

Evaluate how important Critical Path Analysis (CPA) is to the success of the hard rock mine.

Worked solution & mark scheme

This 16-mark question has a full step-by-step worked solution and mark scheme. One marking point: Total float is the greatest amount by which an activity may be postponed without putting back the project completion time.