(a(i))[3]
Calculate the total float available for activity C.
(a(ii))[1]
Identify the minimum project duration from the information given.
(b)[12]
Evaluate how important Critical Path Analysis (CPA) is to the success of the hard rock mine.
Business 9609 · AS & A Level · The nature of operations
Calculate the total float available for activity C.
Identify the minimum project duration from the information given.
Evaluate how important Critical Path Analysis (CPA) is to the success of the hard rock mine.
This 16-mark question has a full step-by-step worked solution and mark scheme. One marking point: “Total float is the greatest amount by which an activity may be postponed without putting back the project completion time.” …