(a)[8]
See Appendix 1.
- Draw a network diagram for the new factory project. [4]
- Identify all the earliest start times (ESTs) and latest finish times (LFTs) for the activities. [4]
(b)[12]
Discuss whether the Operations Director is justified in being confident that the new factory project will be completed in 23 weeks.