(a)[1]
Calculate the minimum duration for the project.
(b)[3]
Calculate the total float of activity D.
(c)[12]
Evaluate whether critical path analysis (CPA) will ensure CP achieves its objective of minimising interruption to production.
Business 9609 · AS & A Level · Location and scale
Calculate the minimum duration for the project.
Calculate the total float of activity D.
Evaluate whether critical path analysis (CPA) will ensure CP achieves its objective of minimising interruption to production.
This 16-mark question has a full step-by-step worked solution and mark scheme. One marking point: “Correct minimum duration for the project (CP = 13 weeks).” …