Location and scale — practice question

(a)[6]

Refer to Appendix A (reproduced from the insert). Calculate the following values for the network used to assemble a kit house:

  • Overall duration of house assembly [2]
  • Free float for activity H [2]
  • Activity F total float [2]
(b)[12]

Evaluate the role that critical path analysis (CPA) has in meeting QH’s quality targets.