Location and scale — practice question

(a)

Look at Appendix 1. Calculate:

  • earliest start time (EST) of Activity F [2]
  • total float of Activity D [3]
  • free float of Activity C [3]
(b)[12]

Assess the role of critical path analysis (CPA) in the successful installation of the new coffee roasting machines.