Business 9609 · AS & A Level · External influences on business activity

External influences on business activity — practice question

(a)[8]

Use Table 3 and Appendix 1 as references:

  • Complete nodes 3 and 4 on the network analysis below (reproduced from the Insert). [4]
  • Identify the critical path. Please write your answer below. [1]
  • Calculate the minimum time needed to complete the project to open Alderly Gardens. Write your answer below. [1]
  • Calculate the total float of Activity J. [2]
(b)[12]

Evaluate the usefulness of network analysis to HBG when it is making operational decisions.

Worked solution & mark scheme

This 20-mark question has a full step-by-step worked solution and mark scheme.

  • Full mark scheme, point by point
  • Step-by-step worked solution
  • Write your answer & get it marked instantly by AI