(a)[6]
Use Table 2 and Fig. 1 as the reference points.
- Finish node 5 on the network diagram, using the Insert. [2]
- Identify the minimum project duration if there are no delays in the project. [1]
- State which activities lie on the critical path. [1]
- Calculate the total float of Activity J. [2]
(b)[12]
Evaluate the usefulness of critical path analysis (CPA) for UBH when planning the opening of new centres.