External influences on business activity — practice question

(a)[6]

Use Table 2 and Fig. 1 as the reference points.

  • Finish node 5 on the network diagram, using the Insert. [2]
  • Identify the minimum project duration if there are no delays in the project. [1]
  • State which activities lie on the critical path. [1]
  • Calculate the total float of Activity J. [2]
(b)[12]

Evaluate the usefulness of critical path analysis (CPA) for UBH when planning the opening of new centres.