The table shows data supplied by a company. budgeted direct labour hours: $8000$ actual direct labour hours worked: $7500$ budgeted overhead expenditure: $104\,000$ actual overhead expenditure: $112\,500$ Calculate the over or under recovery of overheads?
- A$8500$ over recovered
- B$8500$ under recovered
- C$15\,000$ over recovered
- D$15\,000$ under recovered