The table presents the production figures for one week. Forecast production: 10 000 units. Forecast production overheads: $50 000. Actual production overheads: $60 000. Under absorption of overheads: $5000. What was the actual level of production in that week?
- A9000 units
- B9167 units
- C11 000 units
- D13 000 units