A chemical plant manufactures a batch of 50 000 units. Direct materials cost $400 000. Direct labour amounts to 1000 hours at a cost of $60 000, and overheads are absorbed at $60 per direct labour hour. What is the cost of one unit?
- A$8.00
- B$9.20
- C$10.40
- D$14.00