X Limited has forecast monthly overheads of $125 000. Its overhead absorption rate is $5 per machine hour. In July, overheads were under-absorbed by $1000. Which differences from the budgeted figures caused this outcome?
Accounting 9706 · AS & A Level · Traditional costing methods