Accounting 9706 · AS & A Level · Standard costing

Standard costing — practice question

Mohindra uses a standard costing system.
(a(i))[2]

Work out the material price variance for October.

(a(ii))[2]

Work out the material usage variance for October.

(a(iii))[2]

Work out the labour rate variance for October.

(a(iv))[2]

Work out the labour efficiency variance for October.

(b(i))[4]

Analyse, using your answer from part (a), how the material price variance and material usage variance are connected.

(b(ii))[4]

Analyse, using your answer from part (a), how the labour rate variance and labour efficiency variance are related.

(c)[4]

Explain to Mohindra how this variance can be broken down to give him extra information about how his business is performing.

(d)[5]

Advise Mohindra whether to adopt this course of action or not. Support your response.

Worked solution & mark scheme

This 25-mark question has a full step-by-step worked solution and mark scheme. One marking point: The working shown is $14\,000 \times 0.25 = 3\,500\text{ F}$.

  • Full mark scheme, point by point
  • Step-by-step worked solution
  • Write your answer & get it marked instantly by AI