Employees receive a basic wage of $\$10$ per hour. The overtime wage is paid at time and a half. A bonus is paid at a rate of $10\%$ of basic pay if production is above target. For one month, the data are: total hours worked = $1500$, hours paid at the basic rate = $1000$, target production = $12\,500$ units, actual production = $15\,000$ units. What was the total factory labour cost for the month?
- A$\$16\,500$
- B$\$18\,500$
- C$\$19\,250$
- D$\$24\,750$