A business hires machine operators. Each machine operator works $36$ hours per week. Making one unit of output requires four hours of labour. It also has supervisors, and each supervisor can oversee ten machine operators. Output is now $1140$ units per week. How many extra units can be made each week before the company must hire an additional supervisor?
- A3
- B30
- C75
- D90