The total production wages paid during the year were $\$257\,000$. Indirect wages accounted for $30\%$ of the total. Direct workers were scheduled to complete $15\,000$ hours, but they actually completed only $13\,000$ hours. There were no overtime payments or bonus payments. What is the hourly rate of pay for direct labour?
- A$\$5.14$
- B$\$5.93$
- C$\$11.99$
- D$\$13.84$